We anticipate that it will take four to six weeks to chipseal all programmed areas in this order:
Area bounded by Park Avenue to Campbell, Fair Street to Irvington
Area bounded by I-19 to 12th Avenue, Drexel Road to Valencia
Area bounded by Shannon Road to La Cholla, 36th Street to 44th Street
Area bounded by Campbell to Tucson Boulevard, Elm Street to Speedway
Notification to affected neighborhoods commenced on Monday, March 5, 2012 informing them of our intended start date.
Sweeping of the first chipsealed area will begin March 15, 2012.
A fog seal application will then be scheduled for all chipsealed locations, with an estimated completion date of June 1, 2012.